Reconstruct and renovate customer service building in Ardiya for Ministry of Electricity & Water & Renewable Energy
Kuwait National Guard Supermarket Extension Project
Completing the implementation of the central market expansion
And furnishing shelves and refrigerators
Al Somoud camp
Tendered by: General Presidency of the National Guard
Start Date: 14/07/2016
Finish Date: 13/11/2017
Budget: KD 1670496.502
About this Project
* Construction of a new one floor building, with an area of 420 square meters.
• Implementing a new compressor room, one floor, with a surface of 40 square meters.
• Implementation of a new construction power station, one floor, with a flat area of 110 square meters.
• Completion of building works and finishes for the executed buildings.
• Changing the décor of the ceilings, dyeing the walls, and making vinyl floors in the existing market.
Related Projects
Expressway Rest Area At Nuwaiseeb
Construction, Completion and Handing-over of Expressway Rest Area at Nuwaiseeb
Camp Arifjan
Construction of 4 buildings for American Army Arifjan Camp on 4000 meter squared plus landscape.